    Mornington Shire Council - NDRRA 2017 Restoration of Road Assets

    About The Project

    Imported Gravel
    Road metres

    Overcoming

    Many Challenges

    Wet Season
    We staged the work to account for the many impacts wet weather has on roadworks projects. Even though the project was impacted with 3 months of wet weather, Spence still delivered the project 2.5 months ahead of schedule.
    Remote Logistics
    Project Management team planned and procured ways to tackle the sizeable importation requirement for material for the project. The team did this through extensive procurement and planning processes to find the best for delivery
    Required Timeframe
    We were given an ambitious completion target from the client due to wet season and funding constraints for the project. Through adequate use of owned and hired resources, Spence delivered well within the requested timeframe.

    What we delivered

    Project Outcome

    Project: MoSC – NDRRA17 – Restoration of Mornington Shire Council road Assets
    Client: Mornington Shire Council
    Value: $13,000,000
    Completion: July 2018
    Project Scope:
    We delivered as part of the Mornington Island NDRRA project the following:

    • Site Setup and mobilisation
    • Delivery, cartage and placement of 40,000t of Heavy Formation Supply, Bulk Fill and Gravel sheeting material via Barge within 10 weeks
    • Pothole Repair and clearing out of culvert structures
    • Grading, placement and compaction of gravel sheeting
    • Medium Grading of existing roads – 30km
    • Heavy Grading of existing roads – 50km
    • Management of impassable road network prior to commencement of works
    • Concrete floodway’s, box culverts and various other structures